WALL
RECOVERING WITH PORCELAIN TILES
Sticky
Plaster Process
Prepare
surface for tiling.
The
wall should be covered with plaster, then leveled and smoothed.
The
plaster should be prepared within more than 14 days, according to
NBR 8214.
The
plaster should be free of abrasives, oil, paint, and any other particles
that may inhibit adherence.
The
plaster should be made of cement, lime, and washed sand between
1:1:6 and 1:2:9, according to NBR 8214; or it should be industrial
plaster with the same characteristics.
The
plaster should contain the anticipated movement joints, as outlined
in NBR 8214.

-
Prepare surface for tile
- Prepare sticky plaster
- Prepare nata of tiles
- Install tiles
- Remove paper and glue
- Adjustment
- Cut tile plates
- Final clean-up